Cable Replacement
JOB-2026-0169 - raised via Phone 5 mo ago
CompletedNormal priorityCommercial Pro AMC
Checklist
6 of 6 steps complete
Findings
Defects recorded on site. Unresolved criticals roll up to the operations overview.
Burnt MC4 connector
CriticalDC connector on string C shows arcing damage. Replaced on site and adjacent connectors re-terminated.
Open
String mismatch on MPPT 2
MajorString currents differ by 18 percent, pointing to partial shading or module degradation.
Resolved
Parts used
Consumed from van stock on this visit.
No parts consumed
Result
Generation either side of the visit.
+21 kWhper day
77 kWh before, 98 kWh after
Worth about Rs 28,350 a month at this site's tariff.
Assignment
Technician
Waqar AhmedDetails
- Customer
- Pak Agro Farms
- City
- Karachi
- Capacity
- 25.0 kW
- Raised
- 16 Mar 2026, 11:00 AM
- Scheduled
- 16 Mar 2026, 2:00 PM
- SLA due
- 16 Mar 2026, 7:00 PM (5 mo ago)
- Completed
- 16 Mar 2026, 2:00 PM
- Services
- Cable Replacement
- Amount
- Rs 12,160