JOB-2026-0147 - raised via Portal 2 mo ago

CompletedNormal priorityCommercial Pro AMC
Checklist

6 of 6 steps complete

Findings

Defects recorded on site. Unresolved criticals roll up to the operations overview.

  • Earthing resistance above limit

    Major

    Measured 9.4 ohm against a 5 ohm reference. Earth pit needs re-treatment.

    Resolved

Parts used

Consumed from van stock on this visit.

PartQtyUnit costLine total
Mid Clamp 35mm4Rs 39,203Rs 156,812
Result

Generation either side of the visit.

+17 kWhper day

422 kWh before, 439 kWh after

Worth about Rs 22,440 a month at this site's tariff.

Assignment

Technician

Shoaib Akhtar
Details
City
Islamabad
Capacity
150.0 kW
Raised
19 Jun 2026, 8:00 AM
Scheduled
19 Jun 2026, 12:00 PM
SLA due
19 Jun 2026, 4:00 PM (2 mo ago)
Completed
19 Jun 2026, 12:00 PM
Services
Warranty Claims
Amount
Rs 4,500