Bird Dropping Removal

JOB-2026-0083 - raised via AMC schedule 1 mo ago

InvoicedNormal priority
Checklist

6 of 6 steps complete

Findings

Defects recorded on site. Unresolved criticals roll up to the operations overview.

  • Burnt MC4 connector

    Critical

    DC connector on string C shows arcing damage. Replaced on site and adjacent connectors re-terminated.

    Resolved

Parts used

Consumed from van stock on this visit.

PartQtyUnit costLine total
SPD Type 2 DC2Rs 31,674Rs 63,348
Result

Generation either side of the visit.

+3 kWhper day

37 kWh before, 40 kWh after

Worth about Rs 4,590 a month at this site's tariff.

Assignment

Technician

Danish Ali
Details
Customer
Ayesha Malik
City
Faisalabad
Capacity
12.0 kW
Raised
8 Jul 2026, 3:00 PM
Scheduled
8 Jul 2026, 10:00 PM
SLA due
11 Jul 2026, 3:00 PM (1 mo ago)
Completed
8 Jul 2026, 10:00 PM
Services
Bird Dropping Removal
Amount
Rs 3,500