Performance Optimization
JOB-2026-0028 - raised via WhatsApp 6 mo ago
CompletedNormal priorityCommercial Pro AMC
Operations console
JOB-2026-0028 - raised via WhatsApp 6 mo ago
6 of 6 steps complete
Defects recorded on site. Unresolved criticals roll up to the operations overview.
Hotspot detected on string B
Thermal scan shows a cell running 27 degrees above array average. Bypass diode failure suspected.
Open
Consumed from van stock on this visit.
| Part | Qty | Unit cost | Line total |
|---|---|---|---|
| Soft Wash Brush Head | 4 | Rs 4,461 | Rs 17,844 |
Generation either side of the visit.
277 kWh before, 328 kWh after
Worth about Rs 67,320 a month at this site's tariff.
Technician
Shoaib Akhtar