Lightning Protection
JOB-2026-0027 - raised via Website 7 days ago
CompletedLow priorityQuarterly Care AMC
Operations console
JOB-2026-0027 - raised via Website 7 days ago
6 of 6 steps complete
Defects recorded on site. Unresolved criticals roll up to the operations overview.
Earthing resistance above limit
Measured 9.4 ohm against a 5 ohm reference. Earth pit needs re-treatment.
Resolved
Consumed from van stock on this visit.
| Part | Qty | Unit cost | Line total |
|---|---|---|---|
| Lightning Arrestor | 3 | Rs 35,058 | Rs 105,174 |
| Thermal Paste Tube | 1 | Rs 16,819 | Rs 16,819 |
Generation either side of the visit.
37 kWh before, 42 kWh after
Worth about Rs 7,950 a month at this site's tariff.
Technician
Danish Ali