Smart Energy Monitoring App Setup

JOB-2026-0011 - raised via Field survey 6 days ago

CompletedNormal priorityCommercial Pro AMC
Checklist

6 of 6 steps complete

Findings

Defects recorded on site. Unresolved criticals roll up to the operations overview.

  • Inverter derating in afternoon peak

    Major

    Unit throttles above 46 degrees ambient. Cooling fins clogged with dust.

    Resolved

  • Earthing resistance above limit

    Major

    Measured 9.4 ohm against a 5 ohm reference. Earth pit needs re-treatment.

    Resolved

Parts used

Consumed from van stock on this visit.

No parts consumed

Result

Generation either side of the visit.

+111 kWhper day

502 kWh before, 613 kWh after

Worth about Rs 146,520 a month at this site's tariff.

Assignment

Technician

Shoaib Akhtar
Details
City
Islamabad
Capacity
150.0 kW
Raised
12 Aug 2026, 3:00 PM
Scheduled
12 Aug 2026, 7:00 PM
SLA due
12 Aug 2026, 11:00 PM (5 days ago)
Completed
12 Aug 2026, 7:00 PM
Services
Smart Energy Monitoring App Setup
Amount
Rs 6,500