Green Valley School

200.0 kW Hybrid system in Rawalpindi, commissioned 4 Oct 2021

System health

85

Performance ratio against baseline, less open defects

Generated (30 days)

20.2 MWh

89% of expected

Modelled soiling loss

8.7%

Last cleaned 7 Jun 2026

Performance ratio

71.2%

Baseline 80%, target 82%

Generation, expected against actual

Ninety days. The dashed line is the design expectation; the gap between the lines is money.

Soiling loss

Climbs between washes, drops sharply after rain or a clean. The dashed line is the point where a cleaning visit pays for itself.

Performance ratio trend

Against the fleet target.

System specification
Capacity
200.0 kW
System type
Hybrid
Modules
323 x 620W Longi
Inverter
Huawei SUN2000-200K (180.0 kW)
Battery
5 kWh
Tilt / azimuth
14 deg / 200 deg
Bird mesh
Not installed
Tariff
Rs 38 per kWh
Net metering
Approved
NM reference
NM-2026-53094
Sanctioned
200 kW
AMC
Annual Plus
Open findings

Unresolved defects on this site.

  • Monitoring app not configured

    Info

    Customer has no visibility of live generation. App setup offered.

  • Bird nesting under array

    Minor

    Pigeons nesting between modules and roof. Bird mesh recommended for the full perimeter.

Work order history

3 visits

CodeServiceStatusAmount
JOB-2026-0074Electrical Safety AuditScheduledRs 15.0K
JOB-2026-0066Shade AnalysisCompletedRs 8.5K
JOB-2026-0004Hotspot DetectionCompletedRs 1.3L
Inspection reports

No reports for this site

Generation figures are modelled against the design estimate for this system.