Earthing & Safety Inspection

JOB-2026-0092 - raised via AMC schedule 2 mo ago

CompletedNormal priorityAnnual Plus AMC
Checklist

6 of 6 steps complete

Findings

Defects recorded on site. Unresolved criticals roll up to the operations overview.

  • Burnt MC4 connector

    Critical

    DC connector on string C shows arcing damage. Replaced on site and adjacent connectors re-terminated.

    Open

Parts used

Consumed from van stock on this visit.

No parts consumed

Result

Generation either side of the visit.

+25 kWhper day

92 kWh before, 117 kWh after

Worth about Rs 29,250 a month at this site's tariff.

Assignment

Technician

Danish Ali
Details
City
Faisalabad
Capacity
32.0 kW
Raised
16 Jun 2026, 8:00 AM
Scheduled
17 Jun 2026, 9:00 PM
SLA due
17 Jun 2026, 8:00 AM (2 mo ago)
Completed
17 Jun 2026, 9:00 PM
Services
Earthing & Safety Inspection
Amount
Rs 6,200